Electric buses in Portugal: the 2026 registration boom and funding after the PRR
Electric buses in Portugal had a breakout year in 2026. ACEA counted 642 electrically chargeable buses in Q1 to Q3 2026, up 379.1% on the year before (ACEA).
That was the 6th-highest figure in the EU (Eletrificados). Much of the growth likely comes from deliveries funded by the Portuguese Recovery and Resilience Plan (PRR), although no source ties those deliveries to the registration figures directly.
Below we look at the registration data and the new fleets in Lisbon and Porto, and at what operators say about funding once the PRR money is spent. This article is part of our EVBUS24 series on electric bus adoption country by country.
Portuguese electric bus data come from different sources
Each source counts a different set of vehicles, so check the scope before you compare:
- ACEA: new electrically chargeable buses and coaches over 3.5t, including plug-in hybrids
- DVV: new battery-electric buses over 8t
- ICCT: new zero-emission buses and coaches (battery and fuel cell), plus a separate chart for city buses only
- government and operator figures: buses funded or put into service, which is different from buses registered
Electric bus registrations in Portugal in 2026
| Period | Electric buses | Scope | Source |
|---|---|---|---|
| FY2025 | 235 of 1,082 | ACEA, BEV+PHEV, over 3.5t | ACEA FY2025 |
| H1 2026 | 473 | DVV, BEV over 8t | Sustainable Bus/DVV |
| Q1 to Q3 2026 | 569 (53.4%) | ICCT, ZE buses and coaches | ICCT, Table 3 |
| Q1 to Q3 2026 | 642 of 1,168 (55.0%), up 379.1% | ACEA, BEV+PHEV, over 3.5t | ACEA |
The ICCT figures show how fast the market moved. Portugal registered 569 zero-emission buses and coaches in Q1 to Q3 2026, against 55 (7.0%) in the same period of 2025. In Q3 2026 alone it was 120, or 47.1%.
That puts Portugal 7th in the ICCT ranking for Q1 to Q3 2026, behind Italy (2,053), Poland (935), Romania (862), Germany (858), the Netherlands (783) and France (715) (ICCT, Table 3).
In the DVV ranking for H1 2026, Portugal’s 473 battery-electric buses put it ahead of Romania (343) and France (337) (Sustainable Bus/DVV).
Portugal’s electric share is about double the EU average
For all new buses and coaches, Portugal’s electric share was 53% to 55% in Q1 to Q3 2026: 55.0% electrically chargeable in ACEA’s data (plug-in hybrids included) and 53.4% zero-emission in the ICCT’s. The EU figures for the same period were 26.4% (ACEA) and 27.7% zero-emission (ICCT) (ICCT).
City buses alone go higher. The ICCT’s city-bus chart for Q1 to Q3 2026 shows most new city buses in Portugal as battery-electric, with the rest on natural gas. The ICCT publishes this only as a chart, so we don’t quote an exact figure.
1,006 zero-emission buses for 70 municipalities
The Government of Portugal says financing is planned for 1,006 zero-emission buses for 70 municipalities, with the money coming from the Government and the European Commission (Government of Portugal, 8 September 2026).
Not all of these buses sit in the PRR. The minister said the buses that could not fit in the PRR will also be financed, with national money (Observador, 7 September 2026).
The PRR is Portugal’s part of the EU Recovery and Resilience Facility (RRF). According to the ICCT, RRF funds had to be used by August 2026 (ICCT). For Portugal’s PRR bus measure (C21-i12), the Fundo Ambiental extended the maximum execution deadline of the funded projects to 31 December 2026 (Fundo Ambiental, 30 June 2026).
In our reading, these deadlines most likely explain part of the 2026 spike in Portugal. No source says so directly.
Italy shows the same pattern on a larger scale. The ICCT says the electric share of new EU city buses slipped from 60% in Q2 to 53% in Q3 2026, mainly because of Italy’s RRF-funded Q2 spike.
Carris Lisbon reaches 103 electric buses
Carris, the Lisbon city operator, received 29 new fully electric buses on 7 September 2026. That took its electric fleet to 103 buses, 78 of them funded by the PRR (Government of Portugal). The release does not name the manufacturer of the 29 buses.
STCP Porto puts 30 CaetanoBus e.City Gold into service
In Porto, 30 CaetanoBus e.City Gold 12m electric buses entered service with STCP on 17 September 2026. STCP now runs 126 fully electric buses, about 28% of its operation (STCP).
The order dates from 2025. The €11.67m contract covers the 30 buses plus a depot charging station with 15 double chargers (STCP; CaetanoBus). STCP puts the investment at about €12m, with about €7m from the PRR and about €5m from its shareholder municipalities.
Carris Metropolitana expects no new e-buses in 2027
Carris Metropolitana runs buses in the wider Lisbon metropolitan area. It is at 14% electric, up from less than 5% in 2019, with a target of 100% by 2030 (RTP).
In October 2026 operator Rodoviária de Lisboa presented 37 new electric buses for the network. The metropolitan authority TML, however, expects no new e-buses in 2027 and more only in 2028, with no numbers given.
The Secretary of State for Mobility says the government is studying new funding options and expects new EU support. No successor programme has been published yet.
For context, RTP cites IMT data from 2023: at that time about 2% of passenger buses in Portugal were electric.
Electric bus manufacturers in Portugal
No brand split for Portuguese e-bus registrations has been published. The only supplier we can confirm is CaetanoBus, for STCP’s 30 buses.
Across Europe, Chinese brands took about 34% of battery-electric bus registrations in H1 2026 (AutoNext). The European Commission’s Public Procurement Act proposal of 9 September 2026 would let public buyers reject bids in which EU or covered-country content is less than half of the contract value (EPRS). It is a general rule, with no bus-specific thresholds (Sustainable Bus).
What bus suppliers should expect in Portugal after 2026
The 2026 figures show what Portuguese operators buy when the money is there. The market went from 235 electrically chargeable buses in FY2025 to 642 in only nine months of 2026.
What happens next depends on funding decisions that haven’t been made. Before you plan sales or service capacity for Portugal, check:
- what new funding the government announces after the PRR
- how many of the 1,006 planned buses are already registered and how many are still to come
- when Carris Metropolitana and TML open their next electric bus procurement
- which manufacturers supplied the 2026 batches, as this data is not yet published
Portugal after the boom
In Q1 to Q3 2026 ACEA counted 642 electrically chargeable buses in Portugal, up 379.1% and the 6th-highest figure in the EU. Across all buses and coaches the electric share was 53.4% (ICCT, zero-emission) to 55.0% (ACEA), against 26.4% to 27.7% for the EU.
In the cities, Carris is at 103 e-buses and STCP at 126, and financing is planned for 1,006 zero-emission buses for 70 municipalities, from the PRR and national money. The pipeline after that is thin. TML expects no new e-buses for Carris Metropolitana in 2027, and the government is still studying new funding.